Project Progress Assessment And Infrastructure Inspection.
Project Progress Assessment And Infrastructure Inspection. #Rainprotectionstructure (#Greenhouse) Size 220Ft X 100Ft.
24 August 2024 | Saturday: Representatives from the #MyVentureProperty (MVP) team conducted an assessment to evaluate the progress of the #greenhouse construction project in Semenyih. The evaluation involved aspects such as physical progress, work quality, adherence to the schedule, and issues encountered during the project’s implementation.
Overall, the greenhouse construction project was able to proceed according to the set schedule, despite facing challenges such as heavy rain and extreme temperatures.
With the installation of this greenhouse, MVP can ensure an ideal environment for cultivating over 2,000 #chili seedlings using advanced #fertigation technology. The fertigation system is a combination of irrigation and fertilization that delivers #nutrients directly to the plant roots through irrigation water. This enhances the efficiency of water and nutrient usage while promoting healthy and productive chili growth.
#MVP offers Rain Protection Structure construction costs of various sizes starting from:
- RM6.50/sqft (1 acre)
- RM6.00/sqft (2 acres)
- RM5.00/sqft (3 acres)
- RM4.80/sqft (4 acres)
- RM4.00/sqft (6 acres)
For those interested in installing a #greenhouse and have land to be developed, you can contact us for more information and a quotation!
https://www.wasap.my/601162727287/myventureproperty